Campus Construction Activity

Campus Construction Activity


Campus Construction Activity

Campus Construction Projects

 

This map depicts several constructions projects, some already underway, that will occur this Spring 2014 semester and into the summer on Lower Campus and Upper Campus.

Both lower campus and upper campus will undergo a series of construction projects this winter leading into spring and summer. Included here are a series of campus plans showing this spring’s more significant construction activity occurring across lower and upper campus. The approximate dates the projects will span are noted on the plans.

  » Please Note: Any changes to the information shown on the plans will be updated as needed.

Upcoming Projects

  • Main Substation Medium Voltage Infrastructure Upgrades: July 21, 2014 - April 21, 2017. Campus Wide impact will be short term duration, and scheduled at a later time.
  • Columbia Hall Roof Replacement: May 1 – Aug. 15, 2014. Replace building roof. Access to building will not be affected. Covered entrances to be provided as necessary. Parking spaces and roadway directly along the east side of the building will be fenced off during construction.
  • McCormick Roof Replacement: April 7 – Aug. 15, 2014. Replace building roof. Access to building will not be affected. Covered entrances to be provided as necessary. Parking spaces directly along north side of building will be fenced off during construction.
  • Waller Telecom Generator: Feb. 17 – May 16, 2014. Access to building will not be affected.
  • Lightstreet Intersection Intersection Reconfiguration: Future Project; Feb. 2, 2015 – April 29, 2016. Provide new turning lanes and added traffic improvements for future expansion of Upper Campus. Traffic patterns will be affected during construction. The campus community will be informed about traffic pattern changes during the construction process.
  • Student Recreation Center Roof Replacement: May 19 – Aug. 15, 2014. Replace building roof. Access to building will not be affected. Covered entrances to be provided as necessary.
  • Stair Replacements; Bakeless, Hartline, Centennial, Maintenance Center: May 19 – Aug. 15, 2014. Replace concrete stairs at these locations. Access to stairs will be affected at various dates and will be announced in advance.
  • Warren Student Services Center Roof Replacement: May 12 – Aug. 15, 2014. Replace building roof. Access to building will not be affected. Covered entrances to be provided as necessary. Access/use of service driveway and entrance to be shared by BU and contractor.
  • Bookstore Lobby Renovations: May 12 – Aug. 15, 2014. Renovate building lobby and receiving areas. Building access is not affected.
  • Elwell Hall Custodial Storage Renovation: Feb. 26 – April 15, 2014. Access to building will not be affected.
  • Scranton Commons Main Dining: May 12, 2014 – Jan. 16, 2015. Renovate upper level dining and servery. Building access is not affected.
  • Carver Hall Walks and Lighting: May 12 – Aug. 15, 2014. Replace exterior lighting, concrete walks, and steps. Access to building, walks, and steps will be restricted at times. Parking and roadway directly along the south side of the building will be affected at times.
  • Sports Stadium Turf Field Resurfacing: April 14 – July 29, 2014. Resurface turf field. No access to stadium during project.
  • Nelson Fieldhouse A Pool Floor Repairs: April 24 – Aug. 1, 2014. No access to pool during construction.
  • Nelson Fieldhouse Floor Repairs: April 24 – July 25, 2014. Lower level floor to be repaired in sections throughout the April to July time period. Off limit areas to be scheduled and posted during project.